Authorization control on Project/WBS

$
0
0

Hello Experts,

 

I have an issue on authorization control project and WBS creation and I seek your guidelines into it.



We have authorization object


 

C_PRPS_VNR  PSPS: Project Manager Authorization for WBS elements


 

C_PROJ_VNR  PSPS: Project Manager for Project Definition


These objects control authorization as per 'Person Responsible' field in our project structure. This is a unique field for project and unique for all WBS elements separately.(Each WBS has a person responsible field of its own) (t-code CJ20N)


We have two departments A & B.

A will create the project and B will create the WBS under it. And department B are having 5/6 users to create WBS elements.


Now, I want to know how this matrix should be set up so that only department A users could create the project and Department B users could only create the WBS for this project.




JUST TO ADD (another view): Can we have some Z-authorization objects which will work in conjunction with the above two authorization object to control the project and WBS creation. Actually, I believe the above to std. objects will work in conjunction with 'Person Responsible' field in project hierarchy. I am just thinking that if department A has 'Z-A' authorization object he/she can create project and if department B has Z-B authorization object in his roles he can create WBS elements.

Looking forward for you suggestions on it.


Thanks for the help.


With Regards

Saurabh